BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
In the matter of: )
) Project No.
WEST VALLEY A & B HYDRO PROJECT )
P‑12053‑001
)
___________________________________)
Scoping Hearing
June 15, 2005
Likely Fire Department
Likely, California
The above entitled matter came on for hearing,
pursuant to notice, at 10:00 a.m.
REPORTED BY:
DANIEL A. HUMPHREY, CSR 5480
BEFORE:
SUSAN O'BRIEN
Fisheries Biologist/Project Coordinator
Office of Energy Projects
Federal Energy Regulatory Commission
888 First Street, NE
Washington, DC 20426
APPEARANCES (CONTINUED):
Frank Winchell, FERC‑Indian Tribe Liaison
Alan Mitchnick, Senior Technical Expert, FERC
Alex Miller, Biologist, FERC
Phil Rhinehart, BLM
Jayne Biggerstaff, U.S. Forest Service
Peter Adams, Hydrologist, Modoc National Forest
Nicholas Josten, applicant
Patricia Cantrall, County Supervisor
and members of the public
June 15, 2005, Likely, California
MS. O'BRIEN: I'd like to welcome
you here today.
My name is a Susan O'Brien. I'm with the Federal Energy
Regulatory Commission in Washington today, A
& B West Valley
Hydro Project.
Also Fisheries Biologist. I want
to thank
you all for coming. This is a public process, and your
input is important. And we are glad you can be here and
thank you for taking the time to
participate.
First I need to do introductions, introduce the
other FERC staff. We will be cooperating, working with BLM
and Forest Service, referred to in the documents
usually as
FS. We
are going to rate the environmental assessment
together.
Scoping, we are here to identify the issues that
we need to address in evaluating this proposed
project.
MR. WINCHELL: Frank Winchell, I
work with the
FERC in Office of Energy Projects. Again that's part of
this office that does relicensing for
hydroelectric
projects.
I'm an archeologist anthropologist, and I do the
cultural resource parts of the proposed project
licensing ‑‑
exemption.
MR. ALEX MILLER: Alex
Miller. I'm a summer
intern at the FERC in DC. Currently I'm a student at
Virginia Tech majoring in Physical and
Environmental
Policies and Planning. So it's an opportunity to see the
real world application.
MR. MITCHNICK: Alan Mitchnick,
Senior Technical
Expert with the Commission. I'll be handling the
terrestrial and endangered species issues.
MS. BIGGERSTAFF: Jayne
Biggerstaff. I work for
the Forest Service in Modoc County.
WOMAN: (unintelligible) I work on Modoc
National Forest Reclamation.
MR. ADAMS: Peter Adams with the
Modoc National
Forest, hydrologist.
MR. RHINEHART: Phil
Rhinehart. I'm with the
BLM, and I'll be working on the problem on the
BLM side.
MS. O'BRIEN: Thank you. Just so you know what
we are doing here today, just go through the
instructions.
Like to go through the processing schedule. Mr. Nicholas
Josten project applicant. And we will turn it over to him
to give a description of the project. Then we will list all
the issues that we have identified. Then we will turn it
over for public comment from all of you, any
discussion.
So as I mentioned, the purpose today is really we
are getting ready to rate your environmental
assessment on
this project, and in order to analyze the impacts
this
project could have and how to deal with that, and
in order
to do that we need to make sure we have
identified all the
issues.
We need to make sure we have all the information we
need to handle that. So we issued our scoping document in
May. If
you didn't get one, there's extra copies as well as
some other handouts. We are here today for the scoping.
The scoping comments are due July 11th. You can e file them
or mail them in, and I will provide you with directions
on
that later.
It's likely that we will need additional
information, and we propose that we issue that in
August.
That's after we have seen all the issues that
have come in,
reevaluate what the applicant has submitted in
his
application, and his additional filings; looking
at other
available information and sources, literature,
studies
conducted by other agencies like the Fish and
Wildlife
Service.
Once we look at all the information we have, if we
feel the applicant needs to gather more
information, we will
write that information request, and plan to issue
it in
August.
Then it's estimated that ‑‑ it's typical we give
90 days for additional information requests. So if we feel
that's the appropriate amount of time, then his
response
would be due in November.
At that point after we analyze everything, then
he would file, and we have all the information we
need to go
ahead with our document, we would issue a notice
saying we
are ready for environmental analysis, meaning we
have enough
information to write our document. And also that notice
also sets another comment period out ‑‑
60‑day comment
period for comments on the project, and
recommendations and
terms and conditions. Some of the agencies, like Fish and
Wildlife agencies, meaning United States Fish and
Wildlife
Service and California Department of Fish and
Game since
this is an exemption, they file mandatory terms
and
conditions.
Like one‑time shot. So
there's a 60‑day time
period that everybody can file comments and
necessary terms
and conditions and recommendations. So potentially those
would be due in January. And then there's another 45‑day
reply comment period. The applicant can file reply comments
as well as anybody else on the comments that were
filed.
And if that all goes well, we should be able to
issue our environmental assessment in April and
be ready for
a Commission decision whether or not to move
forward with
this proposed project, and if so, what measures
we would
require for that project to have. And next spring and
summer should be ready for that Commission
decision on this
project.
This is a exemption rather than a license with
the FERC.
Some of the requirements for an exemption is some
of the structures are already existing
structures, and he's
just modifying, and turbines and powerhouse, so
he qualifies
under the exemption, which is part of the
regulations. And
so he no longer has to file for ‑‑
licenses are usually
issued for a period of time, 30 to 50 years. In 30 to 50
years he does not to have reapply for a
license. This is
it; get this exemption from licensing and with
terms and
conditions that the license or the exemption
order dictates,
and he would still be required, you know, for dam
safety
inspections and such like that there would be the
ability to
reopen that exemption if there are environmental
issues that
require it.
I think that's all I wanted to mention on that.
Do you have any questions on the processing
schedule and about the exemption?
All right. Turn it over to
Nick. Come up and do
your presentation.
MR. JOSTEN: It's on here. Who is in charge of
the computer?
My name is Nick Josten, and my job here is
assigned by Susan just to describe the proposed
project, to
give you folks the clearest idea that I can of
what will
happen, what will be built, and what it will look
like, and
how it will operate. So that's what I'm going to try to do.
I think most of you know the country pretty well.
At least this map is reproduced out in the other
room all
over the place.
There's kind of a recap of the existing
facilities, irrigation facilities. Right now include a
diversion structure located up Jess Valley Road
at the head
of the canyon there. They divert water into a ditch, store
the water in West Valley Reservoir during the
winter, and
then during the summer they release that water
down West
Valley Creek back into the Pit River, and they
use it for
irrigation.
So the dam and the reservoir exists; the ditch
exists, the diversion exists right now.
And this project proposes to take advantage of
those facilities to generate hydroelectric power,
and there
will be two locations where the power is
generated. Here,
the water in the ditch when it's dropped down to
the
reservoir, there is a lot of elevation drop on
the water at
that point.
There will be a power plant at that location.
And then when the water is released from the
reservoir and
brought back to the river there's about another
140 or 150
feet of elevation drop, so there will be a power
plant in
this location.
So the way the water will flow through the
project, it will be diverted at the same existing
diversion,
run down the ditch. At this point currently water flows
down a gully and straight into the
reservoir. We propose to
construct a new canal to bring that water around
up by the
dam, put it into a penstock through a powerhouse,
then into
a reservoir.
Currently the water is released through a pipe
in the dam.
We will attach a penstock to the end of that
pipe so that the water released from the
reservoir will be
pressurized in the penstock and come down just
about to Jess
Valley Road, and at that point it will go through
a second
powerhouse, then back to the river.
So the water flow will be the same as it is now.
The differences will be that the diversion is ‑‑
depending
on the availability of water, will be year
around. And that
this section of the South Fork of the Pit River
will have
reduced flows because the water can only be in
one place.
That's an overview. Then we will
go through what
the facilities look like.
This is just a list of things.
Existing
diversion can be modified to handle the amount of
water. I
have applied for the maximum, 100 CFS. Current water rate
is 38.
This wouldn't make a total of 38.
This 38 comes
first, then an additional 62. But the existing diversion
can handle it with some modifications. We will install a
fish screen on the canal so that all the water
that's
diverted will go through a screen structure to
keep fish out
‑‑ this is a screened canal. This is a piece of a screen
mesh.
This is dictated by National Marine Fisheries
Service.
I'll pass this around. It's a
tight little
screen.
And so all of the water that is diverted will be
screened so fish won't get into the canal. The existing
canal that we use goes about 2.2 miles. There will be a new
section of canal about a half a mile. The penstock that
takes the water from the canal and drops down to
the
reservoir is about 400 feet. It will be 48‑inch penstock,
about so big, above the ground. The powerhouse will be on
the shore of the reservoir. It will be a simple metal
structure about 20 by 50 feet approximate
dimensions. Maybe
ten to fifteen feet tall. It will have two turbines and a
generator.
Then the reservoir of course and the dam exist,
but we will attach a 54‑inch penstock
pipeline to the outlet
of the dam, and that penstock will run down to
Jess Valley
Road and somewhere in there, and there's a lot of
flexibility in the placement of that, there will
be a very
similar powerhouse with two turbines and the
generator.
The transmission line to start at the upper
powerhouse, right about at the dam, cross West
Valley Creek,
run down the road, and join the existing service,
electric
service line that runs down Jess Valley
Road. It needs to
get to Likely.
It will either be built on the common poles
or it will be parallel to the existing line, but
in the same
right‑of‑way.
We can look at each of those facilities. This is
just a little aerial view. This is Jess Valley Road. Most
folks from around here know where this diversion
is. It
will be at the same place. Looks something like this. This
concrete structure is capable of handling 100
CFS, but the
pool size has to be increased to get that much
water
through.
The check dam on the diversion structure will be
raised about eight inches, approximately, in
order to
increase the size of the pool. At high water you won't
hardly notice the difference. At low water ‑‑ you are
probably familiar. There's a small pool that curves behind
that check structure. There's always fish in it.
That will
extend it a little bit further back, but not very
much.
It's just an eight‑inch increase to the
elevation.
The fish screen, I have a slide of
that. The
fish screen will be located a little ways down
the canal.
We were ‑‑ Fish and Game looked this
over and approved that.
The main reason there's just not any room to
build a screen
there until you get a little bit away from the
construction
to the valley, so we will go down the canal a
little ways
and build a fish screen. This is an example of a smaller
screen where there is rotating drums that will be
covered
with that mesh, or that pressed aluminum that I
passed
around.
And that enables it to clean itself.
As it
rotates, stuff accumulates on it, it will dump it
off into
the canal and clean itself. So there's no way for the water
to pass into the canal without going through the
mesh.
This is a picture of the existing
canal. In
places this canal is already big enough to handle
100 CFS.
Other places it will have to be cleaned out and
widened in
order to handle that capacity. And so we will have to go
down the length of it and create that capacity
for 100 CFS
needed.
That will be done by taking materials, when
necessary, from the uphill side of the
canal. We won't
touch the existing dike. That's an old dike that's been
there a long time. In general with canals, the older the
better.
They just get stronger. So we
will avoid any kind
of invasion on that dike.
The other thing is that there are ‑‑ the canals
are imperfect structures. They can fail. They have failed.
This canal failed fairly recently, and everybody
knows about
that.
That can happen with canals. I
cannot guarantee that
that won't happen, but the project has a very
strong
incentive not to let that happen. So what we will plan to
do from the start is to install a liner in any areas
of the
canal that have been historically problems, as we
go. Those
who were on the tour yesterday, I talked about
the material
that would be used for lining.
I brought a piece of it. We can
pass this around
and you can see it, but it's basically a carpet
type
materials; goes into the canal, soil over the top
of it, and
it's impervious.
So we will do that. So there
will be some
improvements to the canal.
Currently the canal runs a long ways.
It's
practically level. When you're driving along the road,
you'll see it along the right. Looks like it's flowing up
hill, but it's essentially flowing level. When it comes to
the divide between the South Fork Pit River and
West Valley
Creek, it dumps over the divide and wash down the
gully into
the reservoir.
That's how the water is currently stored.
Right at that divide we propose to install an
overflow
structure that will move that water out of the
existing
canal into a new canal that will continue to run
around the
top of the hill and bring the water over toward
the dam. In
the event that the project went off line,
couldn't take
water through the powerhouse, it will spill over
at this
point right here and go down into the reservoir
the same way
it currently does. So if there's any kind of a storage
requirement, that can still be met. It doesn't just stop
the whole thing up, but it will be designed to
overflow at
that point where it currently flows in.
This is a low concrete structure.
There's some
fairly significant diversion that's occurred
here, so there
will be some earth moved here to get that
in. But the
structure itself will be just a ground‑level
structure.
This is the other end of that canal.
It's been
brought all the way around the top of the
hill. The canal
will run through a juniper forest. It will be very
difficult to see unless you're right on top of it
until it
comes out at this point right here above the
dam. At that
point we will build an intake structure with
another local
concrete structure, and the water will enter a
pressurized
penstock.
The penstock will run down the hill.
The very
upper part of the penstock is visible from
limited portions
of the reservoir, maybe the first forty, fifty feet. Then
it goes into trees, and when it come out at the
bottom it's
visible again right near the reservoir.
And then that penstock will go into the
powerhouse, and the generators will be located in
the
powerhouse approximately in this photograph
somewhere right
in here.
This is the dam. This is the
existing gatehouse
that they use to release water from the
reservoir. So it
will be all very tight up against the dam. That's going to
be the beginning of the transmission line.
It will probably take one pole to get
it up on
the hill, then come across West Valley Creek and
from that
point on it will run down the existing road.
This is just a little bit of a detail of how the
penstock will look. It will not rest on the ground.
It
will rest on passive saddles. Hold‑on saddles where
necessary.
It's possible in some places ‑‑ the problem out
here is it's very rocky, but if there's soil,
that it can be
partially buried. And also this is the way you could
provide wildlife with an easy path to get across
it.
Originally as proposed this upper pipeline was
quite a bit longer; now it's quite short. Maybe that won't
be a problem, but any of these varieties of
installation are
possible and probably will be used.
Transmission line I talked about.
This is
looking upstream at the dam. And that span of the West
Valley Creek will be right here, on to the road
here, then
it will be on the road the rest of the way
down.
Now we are starting to look at the lower
project.
This is the current facility for releasing water
from the
dam. We
can see this out here yesterday. A few
years ago
you would actually see the gates down at the
bottom, the
reservoir was so low. But you open and close the gates from
that gatehouse that sits up on the side of the
reservoir,
and that will be opened up fully. And the release from the
reservoir will be performed at the powerhouse
down at the
bottom.
So this structure won't go way, it will still be
there. It
will be retained in operating condition, but it
will be left open, and the actual regulation of
water will
occur in the hydropower project.
This is where the pipe comes out of the dam at
this point we connect onto it with a new
pipe. There will
be a valve in that area so you can put some water
in the
creek and some into the pipeline, or all the
water in the
creek or all the water in the pipeline. There will be a big
butterfly valve down there that permits you to
move the
water each way.
The reason that is important is because the
irrigation district has a ‑‑
occasionally will release for
irrigation purposes more water than the hydro
project can
handle, so you have to have a way to get the rest
of that
water down.
So this will have the capacity to give you all
the water that it can currently deliver. Bypasses
essentially that valve. It will be located just right down
below the dam.
Okay. At that point we have
water in a penstock,
and we will slowly edge that penstock over on to
the road.
The road's dropping down. The penstock holds more or less a
constant elevation. At some point it will be at road level.
Then we will put it on the road and keep it on
the road for
the rest of the way down to the river. And the construction
of this will be similar. It will depend on the substrate
conditions, whether it be a combination of hold‑downs
and
passive saddles and possibly partially buried
segments.
The lower powerhouse then is going to be located
somewhere in the vicinity of the confluence of
West Valley
Creek and the South Fork of the Pit. There's a lot of
options available for how to do this and where to
place
this. And
there was some discussion about this yesterday,
and it's conceivable that that powerhouse can be
pushed up a
little ways into the existing vegetation where it
will be
practically invisible from the road. That's something we
will certainly look at. That has to be weighed against the
drop that you get in the water pressure, so these
last few
hundred feet is about two percent of the overall
drop. So
there's a trade‑off there that we will look
at. There's a
lot of flexibility in selection. Probably not even in the
running is an old picture and more likely be over
on the
other side of the road somewhere just above the
confluence.
Similar building. Metal building somewhere in the order of
20 by 50 feet.
And inside it will be two turbines and a
generator.
The transmission line has come down the road,
then it will join that existing transmission line
right of
way that's been there. We can combine those poles.
That's
something that the rural electric is interested
in. There
will still be just one set of poles with the
transmission
lines and the service lines. They have suggested that they
were interested in that. The lines can be turned over to
them after they are built so they will be able to
provide
three‑phase power all the way up to the
reservoir. If not,
it will be a parallel line in the same right of
way.
The water. These graphs are on
the walls, and if
people have questions about these, it's probably
best to
stand and look at them, talk about them, because
there's a
lot of information in them. But I'll just go briefly over
the water information.
This is based on 1990 to 2002.
They have water
records in the South Fork of the Pit all the way
back to
1920. But
in order to understand how water flows through
this system you also have to know how much water
has been
diverted by the District and how much water has
been
released by the District. And I compiled that information
for 12 years.
So that's the data that we were looking at.
But flows in the main river are available back to
the
1920's.
WOMAN: Did you say that we can
ask you questions
now? Or
did you want to go with your presentation first?
MS. O'BRIEN: Let's finish the
presentation.
WOMAN: Okay.
MR. JOSTEN: There's so much
information in
these. I
guess I'm not sure that there's any one main point
except that this is what it has looked like from
1990 to
2002 with this blue curve being the measurement
as the USGS
station down the entire project. The green curve is the
release from the dam, which there's no release
during the
winter.
It increases during the summer and peaks in the
late summer.
Gray curve is the diversion by the Irrigation
District to store water in the reservoir. Doesn't happen in
the summer.
Starts in November. Captures
storm events and
then it peaks in the spring when the runoff
occurs. So it's
pretty steady storage, then it shuts off
somewhere around
May, and they don't divert in the summer.
Red is the flow in the bypass reach of the
project.
The part of the problem that will be affected by
the diversion.
That's the historic flow.
This is average, same years, assuming that the
project was installed and the diversion up to 100
CFS had
occurred, 100 percent efficiently. You can see that the
water in the river downstream is obviously the
same. Beyond
the confluence of those streams there's no
change. Upstream
from there the amount of diversion is increased
because
there's now diversion for power. The amount of release from
the reservoir is increased because whatever
doesn't need to
be stored will be immediately released for power
generation
and the bypass reach is reduced. There is still a spring
flood.
The flood is smaller; shorter period.
And peak of
the flood is lower. But, for example, when we were out
there yesterday there would still be high water
in the
river.
The power project would not take all of the water.
But it will change that spring flood amount. It will be
small.
That's where the power is coming from.
This one is on the wall. This is
each individual
year model, so you could see what would have
happened each
day.
There's been some dry years and wet years in the last
12. You
can go and take a look at that and try to envision
what it would have been like in a dry year or wet
year or
average year.
Operations. In order to operate
this, there's I
guess the first principle and first priority is
that there's
number one thing that has to be adhered to is the
requirements for irrigation and the requirements
for minimum
flows. So
the first priority in operating this project is
to make sure that water is stored and/or
delivered for
irrigation and that minimum flow requirements are
met. And
you have to adjust the project as required when
the level in
the river changes. So each time the level in the river
changes, the amount of water that you want to
push through
that diversion will change by itself, so you have
to go and
readjust that on a regular basis to make sure
that all of
the requirements are met. And it turns out to be something
that's straightforward to do, but you need some
gauging on
flows.
So as part of this project we will have staff
gauges installed just below the diversion in the
South Fork
Pit so we can measure the bypass flow
directly. We will
have staff gauging in the canal just below the
diversion so
we can see how much is being diverted directly,
and then we
will have a gauge on the amount of water to give
a
measurement.
We are lower of the lower power plant, so we
know how much water is going to come to the lower
project.
I don't have it on here, but there's an existing
gauge in
West Valley Creek, so if there's water in West
Valley Creek,
he can measure that.
So with all the numbers available by reading the
staff gauges that you saw yesterday, you can make
the
adjustment.
As the river changes, the operator of the
project will do that. The operator will also be ‑‑ there
will be an overflow alarm at this point so that
if water was
to overflow, if it was to back up and overflow
into West
Valley Reservoir, the operator would be notified
immediately
so he can go up and make the adjustments. So the operator
will be on this project on a daily basis.
We don't know who that operator will be, but
chances are it will be integrated with the
Irrigation
District's operators currently. That would make sense.
Proposed mitigation. This is
from the list that
Susan and FERC put together and is out
there. There's a
minimum flow requirement that was based on a
study of
in‑stream water depth and flow in the
bypass reach. The
focus of that study was to provide passage for
red band
rainbow trout.
A series of transects were set up and water was
measured and a report was generated and comments
were
received from Fish and Game and the final result
of that is
that 7.5 CFS minimum flow is going to be a
requirement on
this project.
This would be during the parts of the year
when the project diverts for power only. During the winter
wet Irrigation District is diverting for
storage. They have
a different minimum flow requirement. And this project has
no effect on it.
The other thing that they asked for was a ‑‑ in
low water years they wanted a flushing
flowdown: the
requirement of 100 CFS for a 24‑hour
period. This year that
happened anyway.
Even with power project running at full
steam there was enormous flushing flows but
wouldn't have
been important for this year, but some years it
would be
important.
They have entered that as a condition.
The fish screen is a condition that Fish and Game
for retaining fish in the canal. They wanted passage at the
diversion.
At lower water fish can pass over that, if it
becomes too extreme. They wanted a series of rock rubble
weirs constructed so that fish could pass by that
diversion
any time of year.
Talked about installing a canal liner at points
in the canal that have been historically
unstable. That's
one of the things I think the project will do to
make the
canal a more reliable conveyance.
Reseed all bared soil areas with native plants.
Anything that gets stripped of vegetation will be
reseeded
with native plants.
Structures will be colored to blend with natural
background.
I'd be glad to give that choice to anybody who
feels they can make it. I'm probably not the best person,
but we can choose those colors so that it blends
in as best
it can be, and plant free vegetation in case
there's still
some visibility that we want to eliminate.
All the power poles will be raptor proofed, which
means they won't be able to spread their wings
and get one
wing on one and one wing on the other wire. There are
standards for that common in the industry.
And we will need a noise standard.
We will
provide passage across penstocks as needed if we
pick some
kind of a route that's for larger animals. Small animals
will go right under it. We can build passage across the
penstocks.
We will provide an escapement structure in the
canal. In
case an animal got caught in the canal, there
would be a way to get out easily before they come
to any of
the penstocks.
Benefit of the project. It's
clean, renewable
power.
It's not without a price, but it is clean and
renewable power.
There's no pollution. And it's
there
every year.
The maximum capacity of the project is about
2400 kilowatts, 2.4 megawatts at maximum
capacity. That's
enough to power about 2000 average households,
not including
heat.
It's equivalent to 280,000 gallons of Number 2
diesel, 100 million cubic feet of gas. So your power is
coming from somewhere. If it's not a clean and renewable
resource, it's likely one of those others. Somebody else is
dealing with those impacts. But hydropower is clean, it's
renewable, it's very efficient.
The project will also improve the reliability of
the Irrigation District canal. There will be a base also
for the funding source for the maintenance, and I
think
continuous improvement of that canal. Will supply
three‑phase power four miles up county
road. Maybe that's
important to somebody right now. Maybe it will be important
in the future, but it's an expense that will be
handled.
There will be a demand for jobs and services and
primarily during construction, but during
operation and
maintenance it will be another small part of the
economy
here.
I would imagine there's going to be some taxes to
pay, so it's going to be a supplement to the
county tax
base.
Schedule. I don't know if that
syncs with yours
or not.
Looks like it does. If we are to
obtain the
permits by July of next year, there's the
possibility that
we could begin construction by the fall of next
year. Best
case.
Fastest case. And that's
me.
MS. O'BRIEN: Thank you,
Nick.
I just wanted to run through the
issues. Did
anyone write anything on those notes pads?
So we divided it by resource category.
These
issues are listed in the scoping documents, so I
want to run
through them quick.
No? Okay. Nobody wrote anything, so we don't
have anything to add.
For geology and soils. The
issues that are
discussed in the environmental analysis document:
potential
for over topping of canals or canal
failures. And the
effects of project construction and operation on
erosion of
soil in project‑affected water.
For water quality and quantity.
The adequacy of
existing and proposed gages to monitor the
hydrologic
characteristics and compliance with required
minimum stream
flow releases.
The effects of construction of the new project
facilities and modification of existing
facilities on the
water quality.
And the effects of project operations on
water temperature and the other water quality
parameters in
the project‑affected waters.
The effects of the project canal maintenance on
water quality.
Effects of sedimentation and turbidity on water
quality caused by project operations.
Effects of year around water diversions from the
South Fork Pit River required for project
operations on
water quantify in the bypassed reach.
Effects of project construction, associated
land‑disturbing activity. Potential temporary turbidity
increase on the fishing resources in project‑affected
waters.
The effects of project operation on fisheries
resources in project‑affected water.
Effect of the year‑round water diversion from the
South Fork Pit River for project operations on
fisheries.
For terrestrial resources. You
know, the land,
wild land and botanical.
The effects of the loss of up to 35 acres of
vegetation on the local wildlife populations
resulting from
project construction.
The potential for the spread of noxious weeds and
exotic species from construction activities.
And effects of project construction and operation
on sensitive plant and animal species.
The effect of reduced flows in the South Fork of
the Pit River and West Valley Creek on the
existing riparian
communities.
And potential for project transmission line to
pose collision and electrocution hazard to
birds.
Effect on threatened endangered species.
So the effects of the project
construction and
operation on the federally threatened bald
eagle.
Recreation and lands use. The
adequacies of
existing public access and recreational
facilities in the
project area to meet current and future
recreational demand.
The effects of the proposed action and
alternatives on recreational opportunities,
including
off‑highway vehicle use, fishing, boating,
and camping
within the project area.
And the effects of the proposed project
construction, operation, and maintenance on land
use within
the project area.
For scenic and esthetic resources.
Effects of the proposed project construction,
operation, and maintenance on esthetic resources
within the
project area, including noise and visual
impacts.
Effects of shoreline erosion resulting from the
proposed action on the esthetic resources within
the project
area.
Cultural resources.
The effects of project construction and operation
on cultural resources that are listed or
considered eligible
for inclusion in the National Register of
historic places.
Developmental resources and socio‑economics.
The effect of proposed protection, mitigation,
and enhancement measures on the project
economics.
So that's all the issues we have identified. You
can turn in written comments to me personally
today if you
have them ready.
If you want to file them electronically at
the FERC web site or mail them directly. The address is on
the screen, and it's written down in the scoping
documents
which there's copies on the counter, where I can
explain
anything to you after the meeting if you have any
questions
about how to file documents. And they need to be submitted
by July 11th.
We will also take your comments, which is
what we will go into now and the main purpose of
the
meeting.
We would like to hear your comments.
If you have
additional issues you've identified or some
additional
information, that's what we are here for. We don't want to
get into any sort of bad comments or differences
of opinions
and views.
We are here, we would like to hear the
information that you have. So like to keep it friendly and
so we just ‑‑ three people signed up
officially to talk.
Bill, would you like to come up first to talk?
MR. BILL FLOURNOY: I just had a
few comments to
make.
Bill Flournoy, Likely.
I just believe that this project is a good use of
our natural resources. It would be good for the Irrigation
District, it would be good for Modoc County. It has the
potential to increase the tax base by about $2
million, or
near that.
That would be about $20,000 a year to the Modoc
County tax roll.
The Fish and Game has entered into an
agreement with the project that 7 CFS is enough
to maintain
the fish flow, the flow of water needed for
fish. There's a
lot of good fishing in Modoc County in different
creeks
around here that have less than 7 CFS during the
summer.
There's a proposal to get the Fish and Game
involved to make the creek a little better. The best
fishing place in that creek was in the old
through the old
CC camp, and that's where they had some pools
made by the CC
camp years ago, and a lot more could be done to
that. I
have been involved in a little bit of creek rehab
out at the
creek, and the willows and stuff will provide the
shade for
the fish.
Today was nothing there. If they
make some
structures they will slow that water down and
make peace and
might have better fly fishing than we got
now.
That's my comment. Thank
you
MS. O'BRIEN: Thank you. Can you explain where
the CC camp is?
MR. BILL FLOURNOY: Well, it's
right down, right
where that creek gets straight. It's about ‑‑ it's halfway
down.
MS. O'BRIEN: Somewhere in the
middle?
MR. BILL FLOURNOY: People that
live up there
know where the CC camp is. They live right across from it.
MS. O'BRIEN: It's in the middle
of the bypass
reach section?
MR. BILL FLOURNOY: No, it's not
the creek now.
MR. WINCHELL: Can you explain in
a little more
detail what you're talking about as far as the
old CC camp?
Frank Winchell for FERC.
MR. BILL FLOURNOY: You guys have
‑‑ there's guys
that know more than I do, but it's right above
the bridge
that goes to the old Blue Lake Road.
MS. O'BRIEN: So it's near old
Blue Lake Road?
MR. BILL FLOURNOY:
Upstream.
A VOICE: Is this a CC camp? What's the date?
1930's?
MR. BILL FLOURNOY: Yeah. CCC camp.
They built
a swimming hole over there. I think that dam is still
pretty much intact, isn't it?
MS. CANTRALL: The old power
place, a few years
ago.
MR. BILL FLOURNOY: You say
there's no longer a
pool of water?
A SPECTATOR: There's a little pool,
but hardly
any.
A VOICE: A few years ago was
still there. I
haven't been up there for a couple of years. I believe that
is federal land.
MR. BILL FLOURNOY: I believe
it's an Forest
Service land.
A VOICE: Forest Service and
private.
A SPECTATOR: It would be back
towards the east
about quarter of a mile.
MS. O'BRIEN: Jayne, are you
familiar and the CCC
camp?
MS. BIGGERSTAFF: Yeah.
MS. BRUZZONE: Can we ask
questions? My name is
Linda Bruzzone.
I'm a land owner up on the river.
You mentioned $2 million a year revenue?
A SPECTATOR: No.
MS. BRUZZONE: How much is that
revenue that will
be coming in?
A SPECTATOR: I don't know.
MS. BRUZZONE: You work for the
South Fork
Irrigation District; is that correct?
A SPECTATOR: I own land.
MS. BRUZZONE: You're a principal
in this
project?
A SPECTATOR: Not at this
time.
MS. BRUZZONE: I beg your
pardon.
A SPECTATOR: Not at this
time.
MS. BRUZZONE: Have there been
conversations and
a written contract? What is the agreement?
You are for the
canal, right?
What is the agreement with the project
director with the South Fork Irrigation
District?
MR. JOSTEN: There's no
agreement.
MS. BRUZZONE: So they have not
agreed to allow
you to use the diversion canal? What is the agreement with
the South Fork Irrigation District?
MR. JOSTEN: There's no written
agreement.
MS. BRUZZONE: So you have no
permission to use
the diversion canal; is that correct?
MR. JOSTEN: I'm not sure I need
permission, but
there's something that indicates that they will
give
permission.
MS. BRUZZONE: Isn't it true you
told the
landowners appearing at this meeting that the
South Fork
Irrigation District was the principal in the
project?
MR. JOSTEN:
I don't remember the words I used
but I probably told you the truth, which was that
we are
looking at their involvement.
MS. BRUZZONE: Mr. Younger, is
there agreement
between the South Fork Irrigation District and
the
individuals and the project?
MS. O'BRIEN: Could you state
your name for the
record?
MR. YOUNGER: Jay Younger,
Alturas Ranches.
The gentleman that I work for is a large
landowner in the district. He is quite interested in green
projects.
He has several buildings in the San Jose area
that he's converting to solar power. And he became aware of
this project after Nick hooked into it. And he was
interested in it, because in his vision it looked
like a
really good long‑term source of green
energy. And in the
world he lives in there has been considerable
pressure for
that. And
he was just interested in it. So there
have been
discussions between him and Nick. There have been
discussions between the Irrigation District and
Nick. And
there is not a clear vision of how everything
fits together
at this point.
All the parties are currently in agreement that
this is a good project, good for the community,
good for the
District, good for energy. And as everyone here is
concerned, also there is concern about the
effects to the
affected area in the river. And I think we feel that the
mitigation to the wildlife is a huge issue to us
also.
Nothing has been nailed down.
Nothing has been
put in writing.
There has been some financing from Mr.
Swenson, who is the gentleman I work for, that is
totally
unsecured on his part. I have often wondered, you know, why
he does it without an agreement. But he has done it. And
he appears happy to do it.
And we are trying to figure a mechanism to make
in all work.
But it has to satisfy a lot of parties.
You
know, it has to be good for the local economy, it
has to
provide jobs, it has to leave the Irrigation
District intact
with no effect on our diversion rights, nor our
ability to
use that water at the time we want to use that
water. If
there's ‑‑ and then it has to make
money. And it has to pay
for itself.
And of course we have issues with the affected
reach of the river that have to be mitigated
also.
So we are working our way down this road. And it
looks encouraging we could come out to a
successful
conclusion.
This is a project that was envisioned when the
original dam was built. This was a project that was again
looked extensively at in 1980. The District wasn't in a
position to fund the project at that time. And it couldn't
go forward.
And it's again a project that has come up.
Possibly the financing and the people with the
wherewithal
to put it together are currently in place. And it may just
be a project whose time has come.
But we are working on that. We
hope to come to a
successful completion on all of that, and if
possible that's
I think what the District and the most of the
local people
and my owner would like to see happen.
MS. BRUZZONE: Mr. Younger, you
work for Mr.
Swenson directly, can you tell me what control,
what
percentage of the South Fork Irrigation District
he has?
MR. YOUNGER: There's several
principles he's
involved with.
Alturas ‑‑
MS. CANTRALL: Point of
order. Can somebody
answer the question instead of Mrs. Bruzzone
asking three or
four questions at once without waiting for the answer.
Could we hear the answer to each question
please?
MR. YOUNGER: What I'm currently
aware of he is
75 percent owner and Alturas Ranches, which is
roughly 39
percent of West Valley. So he would be 75 percent of 39
percent on that property.
Then he is 50 percent owner in the Estill
(phonetic) property. Which is about 19 percent of the
project.
So he would be 50 percent of 19:
nine‑and‑a‑half
percent.
MS. BRUZZONE: How about Green
Valley Development
Company and his children, what percentage do they
have in
Alturas Ranches according to farm subsidy? They have
something like 86 percent.
MR. YOUNGER: Assuming you're
correct, which I
don't know whether you are or not, then they
would be 86
percent of the 75 percent of that 38
percent.
MS. BRUZZONE: How much of the
voting right does
Alturas Ranches and the other ranch have in the
South Fork
Irrigation District?
MR. YOUNGER: Under the current ‑‑
THE MOTHER:
Did you tell us it was 60 percent ‑‑
THE WITNESS: Wait a minute. I want to answer
this question, okay?
Under the current structure of the Irrigation
District, the entities that I represent have zero
voting
rights in the West Valley Irrigation
District. Under
current rules you have to be a land owner in the
West Valley
Irrigation District, and you have to be a
resident in the
West Valley Irrigation District to be a board
member. And
you have to be a board member to have any voting
rights in
the District.
Now, county wide, there is quite a lot of concern
because since these irrigation districts were set
up in the
'30's when all of the people that owned land
almost always
lived on the property that they owned, and were
represented
because they owned and they lived there, now,
people live in
many different areas within the county but not in
the
district.
And there's tons of confusion there.
So there is
consideration at the county level to change to
try to make
some of those ‑‑ to update some of
those rules.
We have ‑‑ Alturas Ranches have a very good
rapport with the board because they are aware
that we are 38
percent of the district. And they seldom take action
without considering us strongly. But as far as legal voting
rights, the answer is zero. We have input to the board as a
water user.
MS. BRUZZONE: Between the two
ranches, is it
true that you told us it was approximately 60
percent of the
West Valley Irrigation District?
MR. YOUNGER: The two properties,
through
multiple owners, would control I believe 38
percent of West
Valley and 19 percent. And please don't hold me to those
two numbers.
But they are roughly correct.
MS. BRUZZONE: Mr. McGarva, there was an
environmental meeting in Alturas, and you had
mentioned
during that environmental meetings that there was
an
agreement with South Fork Irrigation District
where you were
going to get $20,000 a year that was reported in
the Modoc
Record.
Now, can you tell me where that figure that you
came up with for $20,000 a year during the
environmental
hearing came up from and how you came to that if
there's no
agreement?
MR. McGARVA: Ken McGarva. I'm chairman of the
Board of Directors of South Fork Irrigation
District.
At that time when we were working with Nick, we
had an agreement or part of the proposal that was
had was
that the District would be responsible for the
operation of
the power plant and the release of water. And that was
where the figure $20,000 came up. I think it was in the
studies of the operation and management of
it.
MS. BRUZZONE: So, Mr. Josten was
going to pay
you $20,000 to do the operation of the
plant?
MR. McGARVA: To the
District.
MS. BRUZZONE: That was $20,000 a
year. So that
was an agreement. And the agreement has since changed?
MR. McGARVA: Yeah, after that ‑‑
at the time we
were working on that project, why, the District
decided that
we couldn't go along with the project. And our users voted
it down, to be a part of it.
MS. BRUZZONE: It was voted not
to be a part of
this project?
MR. McGARVA: Right.
MS. BRUZZONE: What was the reason for that?
MR. McGARVA: Mainly was
money.
MS. BRUZZONE: Was he asking for
money for the
project from you?
MR. McGARVA: Oh, yes. Right.
Jay just
mentioned that the part ‑‑ the
$20,000 was our interest in
the project, was interest on it. Nick Josten had 90 percent
of the project.
MS. BRUZZONE: So you are part of
the project or
you were part of the project but now Mr. Josten
is, and we
don't know who else is involved because we don't
have any
partners in it?
MR. McGARVA: No, I don't ‑‑
MS. O'BRIEN: Can I interrupt at
this point. As
FERC sees it, Nick Josten is the only one on the
record as
applicant.
MS. BRUZZONE: Right, my argument
is that we
believe this is violation of state law. We believe that the
South Fork Irrigation District is a public
entity, and
subject to the Brown Act. And there has been no public
notice by the South Fork Irrigation District, no
public
notice to the individuals that will be adversely
effect by
the land.
And we do believe that the South Fork Irrigation
District is involved; that the South Fork
Irrigation
District needs to come forward and let us know
exactly how
they are involved, especially in light of FERC
project P
12575.
That FERC project also shows, if you look at this
map here, it shows another project right at the
end of here
by the South Fork Irrigation District which they
filed, and
down here.
And it shows high wire transmission lines coming
down the West Valley Creek, and those high wire
transmission
lines coming down there. The same things that are addressed
in this project.
We asked the South Fork Irrigation
District for information on this, and they are a
public
entity, and we have not gotten any information on
this. And
it is our concern, and that's why we feel that
these are
possibly two projects combined in one, and we
believe that
there are laws perhaps that apply to this.
MS. O'BRIEN: First I just want
to respond. We
will make sure we get to everybody.
If they're in violation of a county law ‑‑
MS. BRUZZONE: State law.
MS. O'BRIEN: It needs to be
taken up with the
State.
FERC isn't going to get involved in that.
MS. BRUZZONE: Okay.
MS. O'BRIEN: I wanted to
backtrack. I had a
couple of questions. Jay Younger?
MR. YOUNGER: Yeah.
MS. O'BRIEN: When you were
referring to
percentage of the project, I wanted to clarify
you were
discussing percentages of the Irrigation
District, right?
MR. YOUNGER: That's
correct.
MS. O'BRIEN: Okay, because when
we go back and
read the transcript, we will see percentages of
the project.
I want to make sure we understood that's the
Irrigation
District.
MR. YOUNGER: And that is based
on landownership
within the District which is constant for
everybody in the
District.
Each landowner winds up with a percentage of the
water. So
it's backed out of the landownership in the
District.
MS. O'BRIEN: Then you discussed
two of the
owners that are landownerships that are high
percentages.
You referred to two properties, one 60 percent
and one was
19 percent.
THE WITNESS: 38 percent is
Alturas Ranches. And
the 19, if I have that number correct, within a
few percent,
is the Estill property that's on the rest side of
the
valley.
Was the Christensen property before that.
MS. O'BRIEN: Just so we are clear, and I believe
Miss Leslie Murray had a comment about that
issue, so can
you keep you comment to just that issue?
MS. MURRAY: No, I had a
question. Several
people referred to the West Valley Irrigation
District. I
wasn't sure if someone misspoke or if there are
two
different Districts, and maybe I wasn't
aware.
MR. YOUNGER: No, that's a very
good question.
It is South Fork Irrigation District, and that's
my fault.
MS. MURRAY: You just
misspoke?
MS. O'BRIEN: So any reference in
the transcript
to West Valley ‑‑
MR. YOUNGER: Is South Fork.
MS. O'BRIEN: Is South Fork.
And before we go on with the current issue,
there's a couple ‑‑ I wanted to
backtrack. And I had one
clarification for Mr. Flournoy. And I believe Mrs. Bruzzone
was asking this, and I wasn't sure on this. I just wanted
to know the source or how you calculated the
numbers where
you said the increase in the tax base and the
approximate
amount of taxes that would go to the county.
MR. BILL FLOURNOY: I think it's ‑‑
Modoc County
collects one percent of your assessed
valuation. And this
project might reach $2 million, and that would be
$20,000
would be one percent, I think, isn't it?
MS. O'BRIEN: Where did you get
that $2‑million
figure from?
MR. BILL FLOURNOY: That's just
what in general
discussion what I've heard the project might
cost.
MS. O'BRIEN: Okay. Or might be valued at?
MR. BILL FLOURNOY: I'm not
stating a fact
though.
MS. CANTRALL: May I speak to
that? I'm a County
Supervisor, and the discussion has come before
the board.
My name is Patricia Cantrall. I represent this District,
District 3, for the County.
The approximate valuation given by the county
assessor, Mrs. Josephine Johnson, was 1.7 million
to 2.4
million, depending upon the cost of materials and
the cost
of the work done. This is all under permit in this county.
And when the final comes in, that is what the
assessed
valuation rests upon. And we would be collecting for the
tax rolls, the secured tax roll, the one
percent. So it
could be $20,000. It could be greater.
Anyway, she does
keep some figures on file, and we can only wait
until we see
what the project is going to amount to and the
cost thereof
before a final determination can be made.
As to the Brown Act, that is a state law. It is
true you must post meetings of a public
entity. Before the
Bruzzones moved here there were two
meetings. I believe we
have walked the river three times on just this ‑‑
I take
that back ‑‑ twice on this
project. We had some other
dealings with Rodney Flournoy. Those meetings were posted
at the fire hall. They were posted at the post office and
they were reported in the Modoc County
Record. And that was
before the Bruzzones moved here. So they were in compliance
with the Brown Act. And today's meeting also complied.
They have posted all over and noticed in the
Modoc County
Record, the paper of general circulation in this
county.
MS. BRUZZONE: I would like to
make a comment.
My specific reference to the Brown Act was South
Fork
Irrigation District and their participation in
project, not
the notice of this project by Mr. Josten. It has
specifically to do with the South Fork Irrigation
District.
Their meetings, their votes, and their hearings
of actions
that would be adverse to the public and that the
public
needs to know.
The second issue that I'd like to address ‑‑
MS. O'BRIEN: Before we go
further, I believe
there was a couple other comments about the state
issue.
Although I want to comment that FERC can't do
anything about
that. It
needs to be ‑‑ it won't help as far as this issue.
MR. WEISER: I have some comments
to make. They
are a little bit more broad than things that we
are getting
into right now.
So I'd like before you give the floor back
to Linda, but I would appreciate an opportunity
to comment
later how this project affects us.
MS. O'BRIEN: Okay. I have you on the list, and
you submitted your name.
Gentleman in the front had raised his hand when
the issue was first brought up.
MR. FARNAM: Warren Farnam. I just had a
comment.
I just felt we are drifting from the purpose of
this meeting.
MS. O'BRIEN: Okay. Thank you.
MR. FARNAM: And we need to talk
about
environmental scope and scopes of the different
issues, and
I felt like an inquisition of the Water
District.
MS. O'BRIEN: Ms. Bruzzone, did
you have any more
questions?
MS. BRUZZONE: No, I have
comments.
MS. O'BRIEN: You're next on the
list if you want
to move into you comments about this
project.
MR. WEISER: The first map. Dag Weiser.
I'm a property owner on the South Fork Pit River
in the proposed dewatered section. This is my wife Leslie
Murray.
We are not very eloquent. These
are my notes
here. If
everybody will be patient with me, I'll try to go
through some of the things I wrote down this
morning.
Yesterday we went on a walk with a lot of folks,
including John Flournoy and Pat Cantrall, and I
was reminded
of the long history of this area with various
parties, and I
wanted to go on the record, permanent record, as
saying that
my family has a very long history here. I was introduced to
this area by Aaron Forest when I was six. My dad was an Air
Force guy, and his son was in the Air Force. We helped out
his family one time. He introduced us to this area, which I
was just six years old, and I'm 50 now. So it's been quite
a while.
18 years ago the piece of property here came up
for sale.
And it's kind are strange, but this is kind of
where we always used to camp all the years that
my family
came here.
One day a for‑sale sign popped up on that it,
and completely blew our minds. We thought the whole time it
was national forest. We had a long talk. We
pooled our
resources and we bought it.
I also understand that there's a really great
work ethic up here. The McGarvas and the Flournoys.
I'd
like to state for the record that our work ethic
is just as
strong.
We have pooled our family resources in order to buy
this piece of property. And it's our major investment.
It's where we are going to retire. And it means a lot to
us. And
so it's pretty much my whole life is involved in
these acres right here.
How much of the river goes through it?
MS. MURRAY: Three quarters a
mile.
MR. WEISER: Three quarters of a
mile of
dewatered section runs right through this piece
of property.
When I first walked through the door, the first
thing I saw
on the blue piece of paper is the non‑consumptive
wordage.
Personally if I had my way, that kind of thing
would be
completely stricken from the record because if
there is
nothing non‑consumptive about dewatered
area by almost 50 to
80 percent, I can't imagine what's more
consumptive than
that.
Obviously that's a big issue for us.
Obviously our biggest concern is our property
value, and one of the reasons we bought the
property was to
maintain it as a fishery and for anybody to fly
fish on, and
to maintain it in as pristine location as
possible. Haven't
built on it, but our intent is to keep it clean
and the way
that it is.
And we are very concerned about the potential
for the devastation to the three‑mile
stretch of dewatered
thing as a fishery.
It seems like a simple question to me.
But it
doesn't seem to have any simple answer. We want people to
tell me what I noticed from FERC's list of
things, what's
going to happen to this three‑mile stretch
of river.
Something is going to happen to it when a hundred
CFS is
taken out of it year around.
There's no if's, and's, or but's.
It's going to
be hit and I want to know how it's going to be
hit. I want
to know what's going to be affected. Because things are
going to be affected. It doesn't take a brain surgeon to
figure that out.
So far none of those questions have been
answered to my satisfaction. I hope FERC will see that
through.
We talked to a couple of fishermen over the last
couple of days.
To a person, they all thought the idea was
bad from our perspective as a hit to the
fishery.
I stand here today trying to talk for hundreds of
people that use this area recreationally aren't
probably
even aware of what's going on right now.
We were on the walk yesterday, and Edie Asrow
(phonetic), very intelligent person.
MS. O'BRIEN: District
Ranger.
MR. WEISER: Right. Leslie and I both have gone
on the FERC record with tons and tons of comments
on this
thing.
She brought up a couple of brand new ones that I
will comment on today.
And one of them was the ‑‑ oh, yeah, the Forest
Service and all the proponents in charge of the
national
forest.
She was very proud of the fact as she pointed up
and down the river of the work that they have
done in
conjunction with the ranchers and the cattle
folks to
improve huge parts of this potentially three‑mile
diverted
section.
And she says compared to fifty years ago it's like
night and day according to her. I'd like to know what's
going to happen to that 50 years of work when 100
CFS is
taken out of the river. Is it like back to ground zero?
Another point she brought up is, and we were up
on the diversion canal yesterday. And Nick was talking
about beefing up historically troubled spots on
the canal.
I'd like to point out that the historical trouble
spots on
the canal was from the canal that was build for a
38 CFS
partial diversion of water. I don't know if anybody can say
what the historical problems are going to be when
you're
putting a hundred CFS down it year around. The problems
could compound in any number of directions. It wasn't built
for a hundred CFS. The problem that it faces now are
problems it has with the 38, not with the hundred
year
round. So
that's a very big issue to us in terms of safety.
The river took a ‑‑ depending on who you talked
to, you get a completely different opinion from
Jay Younger
than from me on the effect of the current
breach. I
maintain that those effects should be studied,
and I'm
willing to meet anybody half way, but a lot of
the time it's
business as usual in that regard.
And I've got photos to show the extreme siltage
that occurred to that point of pools of water
that I've
fished in for forty years were filled to the top
with silt
that has since washed down with the big spring
runoff we all
had here.
But that had an effect. It
wasn't nothing.
Something happened there, and that wants that to
be
addressed in an environmental way.
And I want potential for a hundred CFS, that's
almost three times that amount of water, to be
addressed
also.
That could be potentially life threatening. Who
knows what could happen there. I'm concerned that those
issues are addressed also.
Another issue I just thought of this morning is
that until a couple years ago I thought that the ‑‑
they
quit stocking the Pit River for the summertime
anglers. I
liked to come up here and fish a little earlier
and fish for
the trout that kind of made it through the last
season
because they are fun to fish for.
I understand there's a big influx in tourist
dollars and anglers coming through here fishing
for those
fun‑to‑fish‑for stocked
trout. I'd really like to know what
Fish and Game, who conspicuously have been absent
from the
meetings and the walk yesterday, and I'm not sure
if there's
any Fish and Game representative here, and tell
me how they
are going to deal with this river as a fishery, a
long time
fishery, with the water levels to the proposed
levels that
the diversion suggests in this ‑‑ for
this project.
From my perspective it might not be viable to
maintain this fishery if the water levels are
that low year
round.
Once again it's just a question of ‑‑ long line
of questions that I keep asking. I have to be brutally
honest and say that my dealings with Fish and
Game, the
South Fork Pit River flies under the radar a
lot. It's a
very small section of stream. The people at Fish and Game
will tell you that resources are stretched to the
maximum.
And they're all over the place. So I'm really having a hard
time getting very simple, what to my mind, very
simple
questions answered to my ‑‑ to where
I can understand it.
I've seen, I don't know where the Fish and Game
currently stocks the summertime trout. Growing up they used
to pull the stock trout trucks right into the big
pool that
is the current diversion. I remember them ‑‑ right above
the diversion there. I remember hundreds of fish pouring
out of these things. Kids, I would go rushing over there
and fish for them right away.
Mr. McGarva yesterday said as we were commenting
on the current diversion, he said that at times
in the year
the current diversion is inadequate for fish
migration. And
I thought about that, and I thought why is this
whole aspect
of fish migration and healthy fish habitat, and
pools and
the fish screens, having to piggyback onto the
project, and
I'd like to ask Fish and Game that. If we are here, but
they are not. Why isn't that area being maintained to this
day as a dangerous place for fish? Why do we have to have a
big power plant in order to get a fish
screen. That doesn't
make any sense to me.
I'd be happy to work with anybody free of charge,
free labor to put up a fish screen at any
time. I'm sure
there's lots of people in organizations all over
the place
that would be happy to get involved in any kind
of fish
screen, healthy area in the existing spot. Until Mr.
McGarva said that yesterday, I had no idea that
area was
inadequate in that regard.
I'll close by saying ‑‑ I won't close quite yet.
I'll say that I understand the proponents' tax
base figures.
I don't understand the figures, but I understand
what we are
trying to say that the project will bring money
into the
area. I
want somebody to say what they think is going to be
lost by the project. Something is going to be lost, or
something may be lost. I want to talk about the if's, and's
and but's of the loss of revenue from a reduced
fishery, of
the loss of my personal private property
values. I paid
plenty of taxes here myself. I'm happy to hear all kind of
comments about what things will do; I want to
hear about
what things might also do in the negative
also.
I was talking with Nick yesterday, and he's
trying to find some common ground where everybody
can be
happy.
It's difficult for me because a lot of the times I
feel that my concerns for my property and the
fish habitat
and trout fishing are so diametrically opposed to
the SFID's
approach to the river. I try to see it from their
perspective.
I try to see it as a thing to use.
From my
perspective it's already being used a lot
currently by the
SFID for their partial diversion, and for a big
part of the
year by everybody else for recreation, for
fishing, and
hopefully for me to live on.
I think that's about it for me.
MS. MURRAY: I'm Leslie Murray,
and I'm Dag's
wife. And
I'll try to not repeat what he's saying, but we
do have some similar interests obviously.
I think very strongly about this obviously. I'm
getting choked up.
MR. WEISER: Take your time.
MS. MURRAY: We don't live here
right now
permanently, but we plan to in the future and we
have been
paying property taxes in this county for fifteen
years on
this piece of property and not really enjoying
many of the
services those property taxes pay for. Certainly if we
build a home, the value of that home as you just ‑‑
as we
talked about, the power plant, and the value of
anyone's
home will also increase the taxes. So if we don't build a
home, that's going to ‑‑ what I'm
trying to say is that any
value of activities that we might do or other
landowners
might do, that we wouldn't do if we didn't care
to live next
to a drained river. That would need to be subtracted from
the figures that you were stating, the one
percent of the
approximately $2 million.
Yesterday when we went on the site visit we heard
a lot about people who live here, and their Modoc
grandparents, and I just wanted to point out that
obviously
we have grandparents too. In fact Dag and I are both third
generation native Californians. We do care a lot about this
area, and do feel like we belong here and that we
know our
way around at least as well as ‑‑
excuse me ‑‑ most of the
other people we were on the site visit with.
And we don't live in a big city now, and we don't
want to.
We live in a small town right now on the coast of
California south of San Francisco. Our family lives by
there.
And I do want to say that we don't own our house
right now.
That this is what we own, and what we plan to do
with our future.
MR. WEISER: We plan on
maintaining this property
for everybody.
I'm not going to put fences up to ‑‑ I'm
going to try to keep the cattle off the property
to keep the
streamside as pristine as possible for
fishermen. My intent
is to maintain it as a fishery because a huge
part of the
dewatered section is some of the best fishing
I've done.
South Fork is an amazingly beautiful and cool
river. You
can go down a hundred yards in the river, you
have a whole
different system going on there. Right in our own backyard
on our property are two completely different
ecosystems, and
each one of those is going to be affected in some
way. And
that's what we want. We want answers to how that's going to
be affected.
There's a shallow, very shallow stretch of
stream, right below ours that's on the Bruzzone's
property
that I believe would virtually cease to exist
with a
potential 100 CFS year round. I understand that all those
figures fluctuate, but I'm talking about a year
round
diversion of 50 to 80 percent of that water.
I've seen things happen on that stretch of stream
of the shallow part that I believe feeds the rest
of
downstream.
When it gets that low, vegetation, hatches,
there's lot of months, there's hatches that happen
on that
stretch of river that I've never seen anywhere
else.
Couple years ago I saw a dragonfly hatch. Had
hundreds and thousands of multi‑colored
dragon flies with
huge wing spans flowing all over the top of the
water. I've
never seen anything like it. I believe that was a real
amazing thing.
I want to know what's going to happen to all
that when this much water is taken out of the
river.
MS. MURRAY: Excuse me. I'm sorry.
I really
feel strongly about this. I had a couple of other points to
make that were notes that I made after we took
the site
visit yesterday which was very interesting. Couple things
that came up in my mind.
One thing was, I'm sorry, about the construction
impact.
And the application starts out by saying that it's
using existing structures, and you kind of just
breeze past
that. In
fact the diversion structure is going to be
enlarged and changed so that the original
concrete block is
there, so maybe technically that's using an
existing
structure, but that seems like quite a lot of
construction
to me, and new things.
The roads are going to be improved.
The canal is
improved.
Half a mile of new excavation.
So I just wanted
to point out my view on that, the term
"existing structure"
is a little bit misleading.
I also agree with Dag. It's
misleading to call
this a non‑consumptive use of three miles
of stream drained
of water ‑‑ I heard up to 93 percent
all year around.
That's consuming of water. I realize this is an
non‑consumptive use. Generally when you're speaking about
different types of power, if you burn coal and
you burn
something, but still to use that term in a way
that implies
there's no impact I think is misleading. The riparian area
permanently changed.
Out of the three‑mile stretch that's proposed to
be drained, virtually drained, one and three
quarter miles
is private property river front. The river goes through our
property at an angle. So that's actually more of the
diversion, slightly more is on private
property. The rest
is national forest.
The water figures of ‑‑ I can't remember the
exact years, but through the '90's. 1990 to 2000, I
believe.
I think that's also misleading.
Someone who was
on the walk yesterday, and I'm afraid I forgot
his name, but
he works for Fish and Wildlife Service from the
Klamath
Falls office.
MS. O'BRIEN: Rick Harney
(phonetic).
MS. MURRAY: Rick told me that
mid '94, '95 was a
record rainfall period for California. So I think that
should be considered when you're considering your
‑‑ the
whole thing that the figures that Nick has given
you might
skew slightly to the higher water. And maybe go in a
direction that's not accurate.
Also that the gauge below West Valley Reservoir,
including the reservoir outflow, obviously you
could do the
math and figure out all the water a lot of people
are
looking at, just those figures, all the figures
are not all
available and all the gages aren't available, and
some of
the gages I've been told are not functioning up
above the
diversion.
There also are various springs, and there's a
spring on our property and seasonal creeks that
add water.
MR. WEISER: That's a really big
issue for us. A
lot of figures we seem to be getting from the
project as far
as potential water from the diversion site don't
include the
seasonal stuff, the springs, and a lot of it are
taken from
a gauge station below where the diversion comes
back in.
One of the few gage stations there. We are real concerned
about the inflow measurements at the diversion
site being
taken into consideration in terms of how much
water is ‑‑
impacts of how much water is being taken
out.
MS. MURRAY: I was also
concerned, obviously this
can probably be checked, but just how all the
gages are
checked, and no one knew for sure. I assume there would be
records with the Irrigation District.
At this point in the project a lot of the details
seem vague, and I would hope that the FERC
process that we
are going through right now would address
those. But that
concerns me that these are vague. The structures could go
here, could go there. Now as we get to speak, yet all these
decisions haven't been made yet. What are we speaking
about?
The true details?
There has been some talk of mitigation of some
discussions, some discussion of what ‑‑
there is activities
offered in situations like this as
mitigation. This is some
stuff that came up yesterday in our site
visit. We spoke
before and met with Nick about a month or so ago,
and talked
with someone that he brought to the meeting about
restoration.
And it turns out ‑‑ well, we can build our own
fences at our own expense anyway, but we can also
seek our
own grant as landowners, so we don't need this
project to
fix things.
Just like Dag was talking about the fish
ladders and different things.
And there was also some talk about trading land,
and I just thought that that sounded like, you
know, taking
this land away that is so special to us is like
if someone
offered to take your husband and get you a new
one that fit
all the same description but wasn't the same
person.
Just to add to the issue of the upgrading, I
think a lot of these upgrades that are being
talked about
really seem like a smoke screen. I know there's a lot of
the government funding, government grants have
been used on
other parts of this river to improve the stream
side and
different things. Using government grants or applicant
funding to fix up the 1935 canal, to upgrade the
diversion
structure, to fix bad roads in the back country
up by ‑‑ on
the way to West Valley Reservoir where the
construction is
going to be, just using ‑‑ it seems
like a culture (?) to
use those properties.
You already talked about the bald eagles. I know
they are planning to make some effort to keep
fish out of
the turbines, but apparently that's not 100
percent, even
though the system appears to limit; that it's not
perfect,
and didn't really like hearing that.
And then the last thing I have to add is on
another topic, that's environmental, but no one
has brought
that up yet.
And I don't know if there's going to be lights
around these structures, but I wanted to say as ‑‑
that I'm
an amateur astronomer, and I know that this area
is one of
the darkest sky locations in the entire
country.
MR. WEISER: It's rated by
astronomy
organizations all over the world as one of the
top rated
dark sky locations in the world.
MS. MURRAY: So having lights on
at night would
really ruin that. They refer to that as light pollution.
And you can look these up. I could show you maps for
organizations that discuss these issues; that
light shining
up in the sky even miles away can affect the
whole thing.
So it's really, really nice to have sky that
dark.
MR. WEISER: The dark sky is a
vast untapped
resource in this area. You know. I'm planning on
making a
astronomy a huge issue for myself.
MS. MURRAY: And would be also
something that
tourists also could come. I can vouch for this. I worked
for a company that sells telescopes for 11 years,
and I'm
well aware of the field trips that people make to
remote
locations in groups. And it's quite a popular hobby, and
this area is an area that has been spoken of by
people that
I've known.
So that's all. Thanks for giving
‑‑
MR. WEISER: Just like to close
by saying thanks
for being so patient as we went through all
this.
I also want to say I have a lot of respect for
some of the long‑time people here. The Cantralls and the
Flournoys and their opinions and what's going
on. What
everybody is trying to do. And I just hope that our
opinions and our concerns are given a certain
amount of
respect and really looked at seriously. I understand the
whole issue of dollars come into the county, and
I'm trying
to pay attention to everything that everybody is
saying, but
I want to pay attention to the stuff that ‑‑
the adverse
effects as well as the potential positive
effects.
MS. MURRAY: I think what we have
to add is it is
good for the county as anything. I know all you guys are
thinking about what's good for the county. I just don't
want our point of view to be overlooked. Thank you.
MS. O'BRIEN: Thank you for your
comments.
Pat, would you like to make your comments?
MS. CANTRALL: Certainly. Patricia Cantrall,
C‑a‑n‑t‑r‑a‑l‑l. We are not the traitors.
I will start with the bottom comment.
You are
certainly true that this is one of the darker
areas. We
have astrologists and astronomers from the
University of
Nevada at Reno who come up to Turlock and the
Great Black
Rock Desert, which as your National Geographic
says is one
of the 44 great deserts of the world.
These gentleman come up and put on light shows,
meaning the star light, for the children at
various
communities and Surprise Valley, and schools at
Alturas
Elementary.
So we do know where that is, and I hold that
dearly because I don't like to go to Susanville
and see the
lights of the prison for miles and miles and
miles.
But anyway, the County of Modoc has been working
on this project.
I only mention the County Assessor and the
tax base it might bring in. We have been planning,
scheduling.
They have some stuff being done by David Alford
(phonetic), the assistant planner, along with our
county
geologist Dr. James E. Slosson (phonetic), who is
the state
geologist for approximately seven years for the
State of
California and did his major thesis when he was a
young man
on the geology and hydrology of the County of
Modoc.
I would need to know the slope, the proposed
slope since that question was asked, and can deer
and other
animals get out of there. Mr. Josten, can you tell me what
the proposed slope of the banks would be?
MR. JOSTEN: Of the canal
banks? One to one and
two to one.
Like they are now.
MS. CANTRALL: About like they
are now. And 2 to
1 slope any animal can get out of. That I do know. We went
through this with 4H and Dr. Slosson would so
state.
Another item as to the posting, we are going to
go back to state law again. I had to dig out my copy of the
Brown Act.
But I would state for the record that the South
Fork Irrigation District again holds its hearings
at the
Likely Cafe on Thursdays. I am the waitress usually working
on Thursdays, and their meetings are posted on
the little
side windows alongside the door. Usually a week in advance.
State law requires 78 hours. So that's five times 24, and
they are posted.
And there are several of us who work in
this community who can verify that. They do not need to be
posted at the post office. That's nice if you want to do
it. But
the posting in the building to be held is all that
is required by state law. So they are posted in a timely
manner.
And I would just like to add that it would be
good in my opinion and not as an old time
resident because I
am not an old time resident. I married my late husband in
1956. I
did not grow up in this community, but I do love
this community dearly. And, you know, it is my job to
support everybody in any way I can, or if there's
a vote
taken, then I must support the majority of the
people who
live here.
I think this would be a good thing in that we
are
all paying quite expensive electric bills because
of the
State of California which we had to buy power
from out of
this state.
Coal in some ways might be a good power source.
There are more things, such as clean coal, than
their used
to be.
But water energy, and I can verify this ‑‑ I also
used to spend summers in Bruney. Beginning ‑‑ PG&E owns
Pits 1 through 7. They had generated much electricity over
the years.
Finally got down to where they didn't really
keep several of these going. So they wished to relicense
those again.
Again I would say to you this is green energy.
This isn't putting smoke into the air, pollution
into the
air.
On the other hand, I realize that, no, you who
live along the river who have just bought those
properties,
you don't want to see the flow diminished, and I
can assure
you that is why we continue to walk the river for
the simple
reason that we need to see what's going on. Nobody is
trying to cut you out of your habitat. Nobody is trying to
cut the deer out of their habitat. And I would argue the
point made by one of my neighbors, Mrs. Sheridan,
who was
worried about the deer not perhaps being
there. Cattle and
deer of an evening will walk from one to three
miles for
water.
They eat all day. You can see
them along the fences
at night up here on the hills coming down to get
water.
That's how predators get it, is when they come
into the
water hole.
I can only state to you as a county supervisor
that I would hope to work with the Indian peoples
with whom
I have gone to school, most of the members of the
local
tribe the landowners here and everyone else, but
I will
state outright that in my opinion this is a good
project if
we can find some way to do it, and I would hope
that some of
the fostering of hate and discontent that has
taken place in
this county like in places like the Brass Rail
act as if in
league with or bought by, that this kind of stuff
will stop.
And that is also a matter of public record all
those that
were there that evening.
So we hope that will discontinue and everybody
can work together to make this project feasible
if at all
possible, and for the greater good of the people
who live on
the river, for the animals, for the environment,
and for all
the peoples of Modoc County. Thank you.
MS. O'BRIEN: Thank you. David Thorne.
MR. WEISER: Can I comment on one
thing she said?
MS. O'BRIEN: Sure.
MR. WEISER: Your concerns with
buying the
out‑of‑state electricity at one time
seem valid, but we have
all read the transcripts of the various ‑‑
of the elevated
energy crisis that we all went through, the Enron
people
talking on the phone about how they was going to
screw
people.
That was a screw of the Californians.
I believe that the energy cries that this project
is trying to piggyback on was a false
crisis. And it's not
happening right now.
MS. CANTRALL: May I answer
that?
It may not be a crisis to you, but the thing is
we are still paying on our electric bills, as are
all
Californians.
If you can't even rent a motel when I'm
traveling on County business anywhere in this
wonderful
state, including the neighboring state of Nevada,
there is
now a surcharge for electricity, and in some
places water.
You may not think the crisis is there, I will
agree with
you, but the point is we are going to continue to
pay until
the day comes when we can say we have water; we
have
electricity.
And that goes mainly for Southern California
because, yes, by God, we do have water and I
intend to hang
on to it.
Either that or send it off in one squirt and let
it flood the government.
Anyway, I could argue that point.
Yeah, we may
not be in a crisis, but you and I are going to
continue to
pay for the next eight years. Whether it goes or not.
MR. WEISER: Whether this project
is actually a
feasible solution to this advanced electrical
crisis in the
future is something that we are all here to
discuss.
MS. CANTRALL: The population of
the United
States is also projected to double by the year
2050. So
there is going to be shortage of
electricity. Thank you.
(Whereupon, a recess was taken.)
MS. O'BRIEN: Okay, so we will
get back to the
meetings.
I just want to again to emphasize that the
purpose of this meeting today is to ‑‑
we are soliciting
comments on this proposed hydropower project and
additional
issues that you may have, or if you have
additional sources
of information for us to help us evaluate this
project.
I believe there's a question for Miss Cantrall.
MR. BROOKE: Richard Brooke, B‑r‑o‑o‑k‑e.
You said that you feel you are representing the
majority.
MS. CANTRALL: No, I said if it
should come down
to a vote, one would have to side with the
majority. That
was clarification. Right now we are not representing
everybody.
We are trying to get all the facts.
A SPECTATOR: Do you believe that
the majority of
people would like to have this project here?
MS. CANTRALL: Within the
district would like to
have the project as it stands now. I can't say that will be
after all the facts are in. A lot of people might change
their mind.
So I can't say that.
But I realize that a lot of you on the river are
against it.
People above you are for it.
South Fork is for
it.
A SPECTATOR: Our fathers are for
it.
MS. CANTRALL: Rodney is who I'm
speaking of.
I'm not saying everybody up there. He is.
And one other ‑‑
you have any other questions, Dick?
All right, the one other thing for notification
to Mr. and Mrs. Bruzzone, since they brought up
this
business.
I forgot to mention and I apologize, that once in
a while there is a meeting at the headquarters of
Alturas
Ranches.
Those meetings are posted on the door of the
building, and they're posted at the Likely post
office, and